General Dynamics Corporation Office Renovations

State-of-the-art Sensitive Compartmented Information Facility (SCIF)

Gilbane partnered with DLR Group to provide design-build services for General Dynamics Mission Systems Division’s new 16,500-SF Sensitive Compartmented Information Facility (SCIF). A SCIF is a secure room that is protected against electronic surveillance. Information can be securely stored, discussed or electronically processed. The build-out consists of two 40-occupant open office spaces, a 3,000-SF data center, an 80-person training room, and support spaces for a new business line within the existing facility. At the start of the project, Gilbane needed to relocate existing infrastructure piping (fire protection, chilled water, and hot water) running through the space to alternate locations around the project area. As the newest build out in Scottsdale, this project serves as a pilot for upcoming renovations at the same location.

Project Overview

  • Gilbane’s dedicated team of mission critical experts guided the client through complex decisions making related to planning, constructing, and managing critical facilities
  • Guided the client through complex decisions making related to planning, constructing and managing critical facilities
  • Offered strategic counsel and construction to minimize downtime and maximize operating efficiency
  • Gilbane was able to significantly reduce the risk of downtime with accurate and actionable information about the power system

Gilbane’s dedicated team of mission critical experts is focused on steering our clients through complex decisions related to planning, constructing and managing critical facilities.

Quick Stats

8

months fast-track construction

17,000

square feet

3,000

square foot data center

Let’s discuss your next project and achieving your goals.

Ask us about our services and expertise.