Terminal expansion project included an addition of 400,000-SF and renovations to the existing facility. The project featured a new, enclosed pedestrian connector bridge to Terminal E to enable circulation between Terminal F and the adjoining terminal complex and proposed the “E” Parking Garage. Gilbane also provided construction management services for the Terminal F single-level hub-airline commuter facility expansion. This compound has 38 commuter gates, 24 of which accommodate a new generation of aircraft. A new terminal space, passenger movement areas, and baggage systems were also added.

Gallery

01 / 03
\

Project Overview

  • Created a continuous secure airside connection between all gates between the International Terminal and Terminal E preventing ticketed passengers from passing through security more than once
  • Maximized capacity and optimize TSA personnel at passenger screening checkpoint with a centralized DOA administration area. Removal of temporary x-ray equipment located in ticketing lobbies to larger facilities in back-of-house and to create ticketing lobbies for additional passenger queuing area
  • Instituted a new in-line EDS baggage screening system with ten x-ray machines, a new security screening area featuring a 14-lane passenger security checkpoint, public circulation on both landside and airside, centralized DOA offices, airport concessions, and a relaxing airline club
  • Executed critical boiler and chiller upgrades in the existing satellite thermal plant and to the existing MEP systems and BAS (Building Automation Systems) controls throughout Terminals D and E

Quick Stats

210,000

Square Foot Connector Building

400,000

Square Foot Addition

38

Terminal Gates