University of Nevada, Reno, Mackay Stadium Upgrades

Historic stadium achieves full ADA compliance

Gilbane provided construction management services for the renovation of the historic, outdoor athletic Mackay Stadium at the University of Nevada, Reno, including bringing the stadium into full ADA compliance.

Gallery

01 / 05
\

Project Overview

  • The stadium seats 30,000 at full capacity but lacked accessible seating
  • Gilbane’s scope of work included building new bleacher platforms, stairs, and handrails to make more sections of the stadium accessible to fans with disabilities

“I myself sat in a wheelchair and toured the stadium to check ramps for accessibility and to review lines of sight, amongst other things. By doing this, I noticed some problem areas that were not addressed in the original plans and provided the owner with ideas for improvement.”

Ian Mastick
Project Engineer
Gilbane Building Company

Quick Stats

30,000

stadium seats

$2M

construction cost

158,000

square feet