New Tactical Equipment Maintenance Facility (TEMF) at Sagami Depot

Expedited shipping of pre-engineered buildings ensures new military complex in Japan is delivered months ahead of schedule

Gilbane constructed a new $28 million, 256,000-SF TEMF complex that includes a maintenance facility, vehicle wash facility, and an organizational storage building. Supporting facilities include a heavy vehicle parking area, weapons storage facility, cargo unloading area, petroleum storage and hazardous waste storage. Gilbane provided site development, facility construction, utilities and connections, lighting, paving, parking, storm drainage, underground detention vaults, an oil/water separator, a diesel fire pump and landscaping.

Gallery

01 / 04
\

Project Overview

  • Mobilized specialized materials and subcontractors from the U.S.
  • Featured PEMB design and fabrication, pre-fabricated hazardous material and petroleum storage buildings, a wash plant, an overhead crane, anti-terrorism/force protection windows and doors, vault doors
  • Electrical panel boards, transformers, and equipment, fire alarm and suppression equipment
  • Provided testing and commissioning teams, and LEED Engineer
  • Engaged all vendors in fast-tracked designs and submittals to gain an early start on fabrication

Gilbane leveraged our experience shipping globally, in accordance with Federal Acquisition Regulation (FAR) requirements, to ensure that all shipments arrived on or ahead of schedule, facilitating the delivery of pre-engineered metal buildings (PEMBs) several months ahead of schedule.

Quick Stats

30

ton gantry crane

3

buildings

256,000

square feet

Let’s discuss your next project and achieving your goals.

Ask us about our services and expertise.