Repair of Runway & Northwest Apron, Offutt Air Force Base

Gilbane leads critical airfield renovation at Offutt Air Force Base

Gilbane successfully managed the complete demolition and reconstruction of the 79-year-old runway at Offutt Air Force Base as part of a $170 million project to bring the airfield up to modern operational standards. The new design features full-depth concrete end sections, an asphalt center section, asphalt shoulders, and a new airfield lighting system to enhance safety and efficiency.

Gallery

01 / 04
\

Project Overview

  • The length of the reconstructed runway is 11,900FT (2.23 miles) and 1M CY of earthwork cut and fill operation was performed on the project
  • Gilbane significantly elevated approximately 35% of a runway by up to eight feet to prevent future flooding
  • Work included concrete and asphalt rehabilitation, new utility relocations, storm drainage, underdrain system installation, as well as sewer, water, power, and communications utilities
  • Project completed on time and in accordance with DoD, Air Force, and NIBS Whole Building Design Guide standards, including CCB and UFC criteria

“In my entire career I’ve never seen a project this size finish on time and on budget.”

Rob Hufford
55th CES Construction Management Chief

11,900

foot (2.23 miles) long reconstructed runway

1M

cubic yards earthwork cut and fill performed

40,000

cubic yards of recycled crushed concrete used